Sunday, January 3, 2010

Work almost finished in Rugerero

We are in the final stretch with the latrine replacements/repairs in the village of Rugerero. Work has been slow and steady over the past few months. To date there have been 27 latrines replaced and 10 latrines fixed in the past 18 months. The plan now is to complete the remaining 5 latrines repairs by January 15th, 2010!! The funds to complete these latrines have been sent to Rwanda. This project has been a learning process for the team.....we are happy to see the project this close to the finish line

The Rwanda team will be traveling again to Rwanda in early February to begin work on the local health clinic latrine and start assessing the nearby Twa village.