Wednesday, December 17, 2008
Slideshows added
Friday, December 5, 2008
Latrine Construction Progress
The team of masons in Rwanda has been busy working on latrines during the last two months. The table below shows a list of completed latrine replacements and repairs. The House numbers corresopond to the numbers on the map (which may be hard to read in this image - sorry).
Friday, November 7, 2008
Latrine Construction Progressing
The masons have continued to work hard on constructing latrines in Rugerero. When the travel team left Rwanda one latrine replacement was complete and two slab repairs were complete. A month and a half later, the following work is complete:
6 new latrines are finished (5 have doors):25W,21E,30E,27W,29W,29W,28E
5 new latrines started and will be done next week:31W,42E,41E,45W,43W
6 slabs repaired :41W,20E,24E,10E,10W,5E
Friday, September 26, 2008
Travel Team Returns to USA, but Work in Rwanda Continues
Photos have been added to many of the prior posts - so you may want to review them. Updates from here on out will be more infrequent.
Please post a comment about how we can improve the blog for future trips - please click on the "comments" link below and answer following questions:
- how often did you check the blog?
- how useful did you find the information?
- how could we make it more informative or interesting? (e.g. more photos, more personal stories, more philosophy, etc.)
Friday, September 19, 2008
Thursday, September 18, 2008
Leaving Gisenyi
After taking the bus to Kigali, we met some Rwandan medical students for dinner - and we all agreed it was the best Indian food we had ever had.
Travel Team Leaving Gisenyi
First Latrine Complete!
Tuesday, September 16, 2008
Wrapping up
Monday, September 15, 2008
Educational materials
Sunday, September 14, 2008
Photos
More Photos
Photos!
Saturday, September 13, 2008
A long walk home
Thursday, September 11, 2008
First Latrine Repair Complete
Here's a typical day for us:
7 AM - breakfast on the veranda overlooking Gisenyi (usually a crepe and eggs)
8 AM - hike around the mountain to the north (Adam calls it the 'freaking mountain') on a short-cut to the taxi stop
8:30 - cram into a van-taxi with 16 others and ride 10 minutes uphill to Rugerero
9 AM - 3 PM - work in the village - lunch is clif bars or nothing
3:30 - catch the taxi back downhill
4-6 PM - shower, relax, tea
6 PM - dinner
7 PM - meet to discuss the day and plans for tomorrow
9 PM or so - head to bed
This has been our schedule so far with some modifications. We work really hard during the day, but have plenty of time to relax and analyze our work plan.
Wednesday, September 10, 2008
The slab looks great!
Tuesday, September 9, 2008
The First New Latrine!
Monday, September 8, 2008
New frustration
Re-using rocks
A Day of Labor
Sunday, September 7, 2008
Update - 2nd mason
This afternoon, we walked around Gisenyl and almost ended up in the Democratic Republic of Congo!
Update - Planning Day
Saturday, September 6, 2008
Update on Rich and Adam
Update on Lora and Linford
Update for Adam & Rich
Wednesday, September 3, 2008
Last Day for the Bobs in Rwanda
The bobs are leaving tomorrow (Thursday). Today we had a good meeting with the health committee. We told them about the change in design and they understood that we are building a strong structure with only one chamber. More of the walls for the latrines have been constructed. They are moving along at a good pace.
Travel Team Obtaining Advice on Structural Design
The form (angle iron beams and roofing material) is only intended to be a temporary structure to hold up the concrete. The concrete will span 2.2 meters and be 10 cm thick. The concrete is reinforced with 12mm rebar on 10 cm centers. The angle iron will be mortared into the wall.
The aggregate available in Rwanda is not the correct size (1.5" aggregate is available but we need <0.75") and we are still trying to determine how to modify the concrete recipe to accomodate.
Tuesday, September 2, 2008
Lora and Linford arrive in Rwanda
The team (BobH, BobDF, Lora, Linford) visited the village today. The Bobs have been doing a lot. They have been working closely with the new mason. He and his team of either 2 to 4 people have been working hard to pour the footing for four of the units. The walls for one of the units was built today. Some of the original walls had to be torn down and rebuilt. They will be meeting with the health committee tomorrow to discuss changes with the design. They have recalculated the cost for all of the latrines and found that the price will be close to $800/latrine - similar to the original estimate. The Bobs have visited the hospital nearby which also has a collapsed latrine. The Bobs have visited a lot of stores too. Shopping is really challenging because all of the stores have different goods. There are not large quantities of anything so sometimes several stores have to be utilized for purchases.
Friday, August 29, 2008
Construction Started
Thursday, August 28, 2008
Modification of Slab Design for Latrines
The current proposal for improving the structure is to pour a single slab (instead of six) and to support the slab with steel beams and metal roofing material. The steel beams will be two pieces of angle iron welded together (to form a T profile) and four beams will span across the pits on 16" centers. Roofing material will be placed perpendicular to the beams in order to support the concrete. The concrete will be reinforced with rebar as in the original design.
There are several advantages and disadvantages to this new design. It will be implemented on the first latrine to determine how well construction proceeds and then a decision will be made whether to continue with the new design or a modification of the old design.
The foreman and laborers are working on putting in concrete footings in the first latrine today and will start building the support walls soon after that. Pouring of the slab should occur early next week.
Tuesday, August 26, 2008
Accomplishments from first 3 days in Rwanda
- Hiring a foreman to oversee the latrine construction - the foreman was recommended by Jean Bosco and is a skilled stone mason (the central wall dividing the pit will be constructed from stone)
- Purchased supplies for the first four latrines
- Visited a shop that can construct the forms for pouring the concrete slabs - the shop can make one form per day - they will make one form and test it this week, then proceed with making six forms total
- Met with community to discuss the plans for latrine construction - the community agreed to provide labor for moving materials and cleaning out the bottom of the pits
We are excited about these achievements in the first few days on the ground. Jean Bosco (from Red Cross) is our primary contact and host in Rwanda - he has been very helpful (this picture shows BobH, BobDF and Jean Bosco on the last trip to Rwanda).
Transportation is being provided using the Red Cross van supplied by Jean Bosco - the van runs on Rwanda time, so the Bob's have had to be patient with getting a later start in the mornings than hoped. They have experimented with public transit, but the van still seems like the best option because hiring our own car and driver is very expensive.
Today, the foreman did not show up in Rugerero as expected but has promised to be there on time tomorrow to start working on preparing a pit and installing the dividing wall.
Generally, the team is a little frustrated that the project is not proceeding as quickly as they would like and the community is not willing to put in as much labor as hoped. We are learning to understand the culture of the community and how best to work with them.
Sunday, August 24, 2008
First Part of Travel Team Arrives in Rwanda
The Bobs are staying in Mama Chalula's guest house in Gisenyi. They have identified a foreman who will begin construction on the latrines on Tuesday. They have met with some the community and some local officals about the project so far.
Some other good news! The money that EWB-USA wired from our account arrived in Rwanda - so the travel team will have access to the funds they need to execute the initial stages of the project!
Tuesday, August 19, 2008
Latrine Repair Project in Rugerero Rwanda
Below is a satellite image showing the homes in Rugerero Rwanda. The homes are colored based on whether their latrines are fully functional, damaged, or non-functional.
Below is a legend for the colors in the map with pictures of typical latrine pits.
Between August 22 and September 20, 2008, the EWB Mid Atlantic Professionals will be in Rugerero to implement a latrine upgrading project. During the trip, EWB-MAP plans to upgrade at least five of the worst latrines based on the design shown below. Latrine upgrades will continue with local supplies and labor over the next year.